Phase 0 EWITA Project Definition Tasks
Task set for Project Planning Phase|
ID |
Task Name |
Duration |
|
1 |
Phase 0 |
288 hrs |
|
2 |
Initial Planning Week |
33 hrs |
|
3 |
Project kick-off |
2 hrs |
|
4 |
Develop team skills matrix |
1 hr |
|
5 |
Discuss architecture definitions |
2 hrs |
|
6 |
Define EWITA project scope |
2 hrs |
|
7 |
Discuss project deliverables |
1 hr |
|
8 |
Discuss/define architecture Critical Success Factors |
3 hrs |
|
9 |
Identify team roles |
1 hr |
|
10 |
Identify information sources |
2 hrs |
|
11 |
Identify Sub-Team approach |
1 hr |
|
12 |
Form Sub-Teams |
1 hr |
|
13 |
Organizational planning/administration |
3 hrs |
|
14 |
Identify benefits of architecture |
2 hrs |
|
15 |
Identify costs/risks of architecture |
2 hrs |
|
16 |
Develop architecture timeline |
2 hrs |
|
17 |
Identify architecture resource requirements |
2 hrs |
|
18 |
Identify project roles |
2 hrs |
|
19 |
Finalize/distribute project status report |
2 hrs |
|
20 |
Forward planning session for week 2 |
2 hrs |
|
21 |
Communications Plan |
54 hrs |
|
22 |
First draft of Communication Plan matrix |
1 hr |
|
23 |
First draft of time/resource template |
1 hr |
|
24 |
Discuss Communication Plan |
2 hrs |
|
25 |
Identify stakeholders (using organization chart) |
2 hrs |
|
26 |
Develop draft Communication Plan |
6 hrs |
|
27 |
Develop project organization chart, responsibilities |
4 hrs |
|
28 |
Finalize drafts |
3 hrs |
|
29 |
Develop Presentation. |
6 hrs |
|
30 |
CIO Review of Draft, (including lead time) |
8 hrs |
|
31 |
Discuss with CIO |
1 hr |
|
32 |
Incorporate CIO's changes |
2 hrs |
|
33 |
Produce Final document, , |
12 hrs |
|
34 |
Quality control |
3 hrs |
|
35 |
Copy, distribute |
1 hr |
|
36 |
Signed-off |
2 hrs |
|
37 |
Project Plan |
81 hrs |
|
38 |
Determine Project Scope |
3 hrs |
|
39 |
First draft due of Project Plan |
24 hsr |
|
40 |
First draft due of Resource Plan |
8 hrs |
|
41 |
First draft due of Project Timeline |
4 hrs |
|
42 |
Combine product |
1 hr |
|
43 |
Reconcile |
3 hrs |
|
44 |
Finalize drafts |
3 hrs |
|
45 |
Develop Presentation. |
6 hrs |
|
46 |
CIO Review of Draft, (including lead time) |
8 hrs |
|
47 |
Discuss with CIO |
1 hr |
|
48 |
Incorporate CIO's changes |
2 hrs |
|
49 |
Produce Final document, , |
12 hrs |
|
50 |
Quality control |
3 hrs |
|
51 |
Copy, distribute |
1 hr |
|
52 |
Signed-off |
2 hrs |
|
53 |
Business Case for EWITA |
52 hrs |
|
54 |
First draft due |
1 hr |
|
55 |
Benefit analysis |
13 hrs |
|
56 |
Finalize drafts |
3 hrs |
|
57 |
Develop Presentation. |
6 hrs |
|
58 |
CIO Review of Draft, (including lead time) |
8 hrs |
|
59 |
Discuss with CIO |
1 hr |
|
60 |
Incorporate CIO's changes |
2 hrs |
|
61 |
Produce Final document, , |
12 hrs |
|
62 |
Quality control |
3 hrs |
|
63 |
Copy, distribute |
1 hr |
|
64 |
Signed-off |
2 hrs |
|
65 |
Project Proposal |
96 hrs |
|
66 |
First draft of "what's in/out" |
1 hr |
|
67 |
First draft of deliverables by phase |
3 hrs |
|
68 |
First draft of component model definition |
3 hrs |
|
69 |
First draft of EWITA TOC |
3 hrs |
|
70 |
First draft of resources by phase |
3 hrs |
|
71 |
First draft of team commitment definition |
1 hr |
|
72 |
First draft of Statements of Work |
3 hrs |
|
73 |
Validate if tracking correctly |
1 hr |
|
74 |
Signed approval |
1 hr |
|
75 |
Discuss Project Proposal |
13 hrs |
|
76 |
Identify resource requirements |
13 hrs |
|
77 |
Identify LOB commitment levels |
13 hrs |
|
78 |
Finalize drafts |
3 hrs |
|
79 |
Develop Presentation. |
6 hrs |
|
80 |
CIO Review of Draft, (including lead time) |
8 hrs |
|
81 |
Discuss with CIO |
1 hr |
|
82 |
Incorporate CIO's changes |
2 hrs |
|
83 |
Produce Final document, , |
12 hrs |
|
84 |
Quality control |
3 hrs |
|
85 |
Copy, distribute |
1 hr |
|
86 |
Signed-off |
2 hrs |
|
87 |
Phase 0 complete |
0 hrs |