Phase 0 EWITA Project Definition Tasks
Task set for Project Planning Phase
ID |
Task Name |
Duration |
1 |
Phase 0 |
288 hrs |
2 |
Initial Planning Week |
33 hrs |
3 |
Project kick-off |
2 hrs |
4 |
Develop team skills matrix |
1 hr |
5 |
Discuss architecture definitions |
2 hrs |
6 |
Define EWITA project scope |
2 hrs |
7 |
Discuss project deliverables |
1 hr |
8 |
Discuss/define architecture Critical Success Factors |
3 hrs |
9 |
Identify team roles |
1 hr |
10 |
Identify information sources |
2 hrs |
11 |
Identify Sub-Team approach |
1 hr |
12 |
Form Sub-Teams |
1 hr |
13 |
Organizational planning/administration |
3 hrs |
14 |
Identify benefits of architecture |
2 hrs |
15 |
Identify costs/risks of architecture |
2 hrs |
16 |
Develop architecture timeline |
2 hrs |
17 |
Identify architecture resource requirements |
2 hrs |
18 |
Identify project roles |
2 hrs |
19 |
Finalize/distribute project status report |
2 hrs |
20 |
Forward planning session for week 2 |
2 hrs |
21 |
Communications Plan |
54 hrs |
22 |
First draft of Communication Plan matrix |
1 hr |
23 |
First draft of time/resource template |
1 hr |
24 |
Discuss Communication Plan |
2 hrs |
25 |
Identify stakeholders (using organization chart) |
2 hrs |
26 |
Develop draft Communication Plan |
6 hrs |
27 |
Develop project organization chart, responsibilities |
4 hrs |
28 |
Finalize drafts |
3 hrs |
29 |
Develop Presentation. |
6 hrs |
30 |
CIO Review of Draft, (including lead time) |
8 hrs |
31 |
Discuss with CIO |
1 hr |
32 |
Incorporate CIO's changes |
2 hrs |
33 |
Produce Final document, , |
12 hrs |
34 |
Quality control |
3 hrs |
35 |
Copy, distribute |
1 hr |
36 |
Signed-off |
2 hrs |
37 |
Project Plan |
81 hrs |
38 |
Determine Project Scope |
3 hrs |
39 |
First draft due of Project Plan |
24 hsr |
40 |
First draft due of Resource Plan |
8 hrs |
41 |
First draft due of Project Timeline |
4 hrs |
42 |
Combine product |
1 hr |
43 |
Reconcile |
3 hrs |
44 |
Finalize drafts |
3 hrs |
45 |
Develop Presentation. |
6 hrs |
46 |
CIO Review of Draft, (including lead time) |
8 hrs |
47 |
Discuss with CIO |
1 hr |
48 |
Incorporate CIO's changes |
2 hrs |
49 |
Produce Final document, , |
12 hrs |
50 |
Quality control |
3 hrs |
51 |
Copy, distribute |
1 hr |
52 |
Signed-off |
2 hrs |
53 |
Business Case for EWITA |
52 hrs |
54 |
First draft due |
1 hr |
55 |
Benefit analysis |
13 hrs |
56 |
Finalize drafts |
3 hrs |
57 |
Develop Presentation. |
6 hrs |
58 |
CIO Review of Draft, (including lead time) |
8 hrs |
59 |
Discuss with CIO |
1 hr |
60 |
Incorporate CIO's changes |
2 hrs |
61 |
Produce Final document, , |
12 hrs |
62 |
Quality control |
3 hrs |
63 |
Copy, distribute |
1 hr |
64 |
Signed-off |
2 hrs |
65 |
Project Proposal |
96 hrs |
66 |
First draft of "what's in/out" |
1 hr |
67 |
First draft of deliverables by phase |
3 hrs |
68 |
First draft of component model definition |
3 hrs |
69 |
First draft of EWITA TOC |
3 hrs |
70 |
First draft of resources by phase |
3 hrs |
71 |
First draft of team commitment definition |
1 hr |
72 |
First draft of Statements of Work |
3 hrs |
73 |
Validate if tracking correctly |
1 hr |
74 |
Signed approval |
1 hr |
75 |
Discuss Project Proposal |
13 hrs |
76 |
Identify resource requirements |
13 hrs |
77 |
Identify LOB commitment levels |
13 hrs |
78 |
Finalize drafts |
3 hrs |
79 |
Develop Presentation. |
6 hrs |
80 |
CIO Review of Draft, (including lead time) |
8 hrs |
81 |
Discuss with CIO |
1 hr |
82 |
Incorporate CIO's changes |
2 hrs |
83 |
Produce Final document, , |
12 hrs |
84 |
Quality control |
3 hrs |
85 |
Copy, distribute |
1 hr |
86 |
Signed-off |
2 hrs |
87 |
Phase 0 complete |
0 hrs |