Component Task Development (7 Components)

ID

Task Name

Duration

Predecessors

1

BDAP Continuation

63 days

 

2

Outstanding Component Architectures

62 days

 

3

Network

30.63 days

 

66

Systems Management

45.5 days

 

129

Transaction Data

30.63 days

 

192

Telephony Component

52.63 days

 

255

Information

32 days

 

256

Groupware

32 days

 

257

Middleware

32 days

 

258

Product Evaluation and Selection Methodology

30 days

 

259

Develop Product Evaluation Methodology

10 days

 

260

Prototype Methodology with Application Dev Tools

20 days

259

261

Consensus Building Process Documentation

9 days

 

262

Process Flow Layout

2 days

 

263

Document Draft

2 days

262

264

Review

2 days

263

265

Update

2 days

264

266

Submit

1 day

265

267

BDA Implementation

63 days

 

268

Incorporate Current Projects

5 days

 

269

Prioritize New Initiatives

10 days

268

270

Begin BDA Maintenance

40 days

269

271

Perform Costing Estimates

10 days

269

272

Perform Scheduling

10 days

269

273

Continue Communications

63 days

 

274

Begin Education

63 days

 

.

Initial Task List

.

 

 

This task list indicates the repetitive nature of the developing architecture, each component in this architecture takes about 32 days. So two architects could do 4 in the 63 day period.. Experience has shown that there is much concurrence that can occur while waiting for meetings, and the time between printed distribution and the meeting.