Sequence |
Task w/I
total project |
Task
Description |
Duration |
Dependency |
0 | 0 | Business Driven Architecture Project (BDAP) | 85.3d | |
1 | 617 | Enterprise Wide Technical Architecture - BDAP | 85.3d | |
2 | 618 | Phase 1 | 27.5d | |
3 | 619 | Begin Phase 1 (Project Mgt./Communication) | 0d | |
5 | 620 | Initiate Enabling Group For Coordinate & Communicate | 1d | |
6 | 621 | Define Mission Of The Team | 2.5h | 3 |
7 | 622 | Define Goals Of The Team | 2.5h | 6 |
8 | 623 | Define Deliverable Of The Team | 2.5h | 7 |
9 | 624 | Assign The Team | 2h | 8 |
10 | 625 | Assign Roles & Responsibilities | 3h | 9 |
11 | 628 | Initiate Enabling Group For Research & Educate (Research
Business & Tech. trends | 1.05d | 5 |
12 | 629 | Define Mission Of The Team | 2.5h | 3 |
13 | 630 | Define Goals Of The Team | 2.5h | 12 |
14 | 631 | Define Deliverable Of The Team | 2h | 13 |
15 | 632 | Assign The Team | 3h | 14 |
16 | 633 | Assign Roles & Responsibilities | 2.5h | 15 |
23 | 636 | Prepare Business Driver Report | 11.9d | 11 |
24 | 637 | Synchronize Business Driver Understanding (Interview Teams) | 1.35d | 10 |
25 | 638 | Define Business Driver Definition | 2h | |
26 | 639 | Assign BDAP Team Members to LOBs | 2.5h | |
28 | 640 | Identify BD Process Owner (LOB BD) | 1h | 27 |
27 | 641 | Identify LOB BD Contacts | 2.5h | 26 |
33 | 642 | Determine BD Training Strategy & Develop Training Content | 2h | 32 |
34 | 643 | Train BDAP Interviewers | 2h | 26 |
35 | 645 | Determine Phase 1 Time lines & Strategy | 6h | |
36 | 646 | Outline BD Report | 3h | 34 |
37 | 647 | Meta Group Reviews BD Report Outline | 2h | 36 |
39 | 648 | Prepare for LOB Interview | 3.9d | 26 |
40 | 649 | Required Preparation | 3.9d | |
41 | 650 | Review EDD Strategic Plan | 5h | |
42 | 651 | Review LOB Annual Business Plans | 4.5h | 41 |
43 | 652 | Review Previous Strategic I/T Efforts | 4h | 42 |
44 | 653 | Interview BCT Contact | 4.5h | 43 |
45 | 654 | Review Meta Box LOB Info | 5h | 44 |
46 | 655 | Finalize Preparation | 2.55d | |
47 | 656 | Outline Research Information Report | 5h | 45 |
48 | 657 | Hold Planning Session w/ BU Process Owner | 1.7d | |
49 | 658 | Validate Understanding Of Business | 10h | 47 |
50 | 659 | Prepare For BD Discovery Process | 10h | 49 |
51 | 660 | Finalize Research Information Report (Meta Review) | 5h | 50 |
52 | 661 | Conduct Interview Process | 3.45d | 39 |
53 | 662 | Prepare Customized Questionnaire & Strategy | 6.5h | 51 |
54 | 663 | Submit Questionnaire To Meta For Review | 2h | 53 |
29 | 664 | Finalize Questionnaire | 3h | 28 |
30 | 665 | Write Interview Letter | 1h | 29 |
31 | 666 | Schedule Interviews | 2h | 30 |
55 | 667 | Deliver Interview Letter With Questionnaire | 4h | 54 |
32 | 668 | Publish Interview Letter | 1h | 31 |
56 | 669 | Prepare and Perform Interview & Receive BD | 32h | 55 |
59 | 670 | Update BD Report | 4.5h | 58 |
60 | 671 | Analyze Information (Core Team) | 1d | 52 |
61 | 672 | Assign Debriefing Assignments | 1h | |
62 | 673 | Prepare for Debrief | 9.5h | 61 |
63 | 674 | Review LOB BD Report w/ Interviewer | 3h | 62 |
64 | 675 | Update LOB BD Report | 3h | 63 |
65 | 676 | Confirm & Prioritize LOB BD Report | 2.75d | 60 |
66 | 677 | Define Time lines for Modifications & Prioritization from
LOB | 5h | 64 |
67 | 678 | Prepare Thank You Letter | 1h | 66 |
68 | 679 | Attach LOB BD To Thank You Letter | 1h | 67 |
69 | 680 | Deliver Thank You Letter & Draft BU BD Report | 4h | 68 |
71 | 681 | Modify & Prioritize Business Drivers (LOB) | 8h | 70 |
72 | 682 | Received LOB Prioritized Modified BD Report | 4h | 71 |
73 | 683 | Finalize LOB BD Report (Meta Review) | 2h | 72 |
74 | 684 | Deliver Final LOB BD Report | 4h | 73 |
75 | 685 | Assign LOB Owner To Each Business Driver | 3h | 74 |
77 | 686 | Prepare Architecture Requirements Report & Matrix 1 (BD x
AR) | 7d | 23 |
78 | 687 | Develop Common Understanding of AR | 1.3d | |
79 | 688 | Define Mission (Purpose of AR) | 2.5h | |
80 | 689 | Train Core Team on AR Facilitation | 7h | 79 |
81 | 690 | Outline Architecture Requirement Document & Matrix | 5h | 80 |
82 | 691 | Develop AR Report & Matrix 1 (BD x AR) | 4.55d | 78 |
83 | 692 | Coordinate AR Development Session | 3h | |
84 | 693 | Identify Information Required to Support BD | 12h | 83 |
85 | 694 | Identify the Processes That Generates The Required Information | 11.5h | 84 |
86 | 695 | Derive AR From Data & Process Input (See EAS Process Model,
Pag 10.) | 23.5h | |
88 | 696 | Update AR Report & Matrix 1 | 10h | 87 |
89 | 697 | Confirm Architecture Requirement (AR) | 1.15d | 82 |
90 | 698 | Define Response Time lines | 3h | 88 |
91 | 699 | Prepare Thank You Letter (Attach LOB AR Report) & Matrix 1 | 1h | 90 |
95 | 700 | Receive LOB AR Edits (Report & Matrix) | 6h | 94 |
97 | 701 | Finalize LOB AR Report & Matrix 1 (BD x AR) (Meta Review) | 5h | 96 |
98 | 702 | Prepare Technology Trends Report | 2.85d | 89 |
99 | 703 | Develop T.T. Report Meta Trends) | 2.85d | |
100 | 704 | Select Tech. Trend Report Author | 1h | |
101 | 705 | Prepare First Draft Of Tech. Trend Report | 10h | 100 |
102 | 706 | Get BU I/T Involvement & Agreement W/ T.T. Report | 12h | 101 |
104 | 707 | Prepare Second Draft Tech. Trend Report | 4h | 103 |
105 | 708 | Review T.T. Report | 2h | 104 |
107 | 709 | Finalize T.T. Report (Meta Review) | 1h | 106 |
108 | 710 | Present Phase 1 Deliverable For Commitment | 3.35d | 98 |
109 | 711 | Give Presentation | 3.35d | |
111 | 712 | Coordinate Meeting Room & Date | 4h | 110 |
112 | 713 | Invite Participants (ITSMT,ITEI,ITDQC) | 2h | |
113 | 714 | Prepare Presentation/Deliverable | 18h | 112 |
115 | 715 | Deliver Phase 1 Deliverable Hard Copy To Attendees | 1h | 114 |
116 | 716 | Execute Presentation Preparation | 3h | 115 |
118 | 717 | Cleanse Phase 1 Deliverable | 5h | 117 |
125 | 718 | Publish Phase 1 Deliverable | 2h | 124 |
121 | 719 | Obtain Commitment to Business Alignment | 0.95d | 114 |
110 | 721 | Define Time lines For Response | 1h | 107 |
124 | 722 | Coordinate and Consolidate LOB Responses | 1h | 123 |
136 | 724 | Phase 2 | 54.55d | 126 |
137 | 725 | Begin Phase 2 | 0d | 108 |
139 | 726 | Initiate Enabling Group For Coordinate & Communicate | 1.1d | |
140 | 727 | Define Mission Of The Team | 3h | |
141 | 728 | Define Goals Of The Team | 2h | 140 |
142 | 729 | Define Deliverable Of The Team | 3h | 141 |
143 | 730 | Assign The Team | 2h | 142 |
144 | 731 | Assign Roles & Responsibilities | 3h | 143 |
145 | 734 | Initiate Enabling Group For Research & Educate | 1.05d | 139 |
146 | 735 | Define Mission Of The Team | 2h | 144 |
147 | 736 | Define Goals Of The Team | 3h | 146 |
148 | 737 | Define Deliverable Of The Team | 2h | 147 |
149 | 738 | Assign The Team | 3h | 148 |
150 | 739 | Assign Roles & Responsibilities | 2h | 149 |
158 | 742 | Prepare Principles - Conceptual Architectures) | 9.35d | 150 |
159 | 743 | Develop Common Understanding Of Principles | 5.1d | |
160 | 744 | Assemble Principles Team | 2h | |
161 | 745 | Define Purpose Of Principle | 4h | 160 |
165 | 746 | Define Principles | 4h | 164 |
162 | 747 | Train Team - | 4.5h | 161 |
163 | 748 | Define Roles & Responsibilities & Time frames | 4h | 162 |
166 | 749 | Outline Principles | 3h | 165 |
167 | 750 | Develop Checkpoint with Josetta | 2h | 166 |
169 | 751 | Develop Principles Report | 4.25d | 159 |
170 | 752 | Review Principles List | 12h | |
172 | 753 | Update Principles Report | 2h | 171 |
173 | 754 | Prepare Best Practices Report & Matrix 2A (AR x BP)
Conceptual Architectures) | 10.6d | 150 |
174 | 755 | Develop Common Understanding Of Best Practices | 5.1d | |
175 | 756 | Assemble BP Team | 2h | |
176 | 757 | Define Purpose Of BP | 4h | 175 |
180 | 758 | Define Best Practice | 4h | 179 |
177 | 759 | Train Team - How to Decompose BP From AR | 4.5h | 176 |
178 | 760 | Define Roles & Responsibilities & Time frames | 4h | 177 |
181 | 761 | Outline BP Report & Matrix 2A | 3h | 180 |
183 | 762 | Checkpoint with Josetta | 1h | 182 |
184 | 763 | Develop Best Practices Report (includes both CIT & DIT) | 5.5d | 174 |
185 | 764 | Review Best Practices List | 12h | |
186 | 765 | Update BP Report & Matrix 2A | 2h | 185 |
187 | 766 | Analyze AR x BP Matrix | 5h | 186 |
188 | 767 | Create Required Best Practices | 37h | 187 |
189 | 768 | Update BP Report & Matrix 2A (AR x BP) | 5h | 188 |
191 | 769 | Checkpoint with Josetta | 2h | 190 |
192 | 770 | Finalize BP Report & Matrix (Meta Review) | 2h | 191 |
193 | 771 | Prepare Component Architecture Report & Matrix 2B (BP x CA) | 10.75d | 192 |
194 | 772 | Develop Common Understanding Of Component Architecture | 1.35d | |
195 | 773 | Validate Phase 0 Component Architecture List | 1h | |
196 | 774 | Accept/Modify Applicable Component Architectures | 1.5h | 195 |
197 | 775 | Identify Component Architecture Owners | 1h | 196 |
198 | 776 | Assemble CA Teams | 1h | 197 |
199 | 777 | Define Purpose Of CA | 1h | 198 |
200 | 778 | Define CA | 2h | 199 |
201 | 779 | Train Team - How to
Decompose CA From BP | 2h | 200 |
202 | 780 | Define Roles & Responsibilities & Time frames | 3h | 201 |
203 | 781 | Define CA Level Of Detail | 2h | 202 |
204 | 782 | Outline CA Report & Matrix 2B | 1h | 203 |
205 | 783 | Develop CA Report | 9.5d | |
210 | 784 | Governance - Create
Component Architectures (Composition) | 9.5h | 203 |
211 | 785 | Update CA Report & Matrix 2B (BP x CA) | 11.5h | 206 |
212 | 786 | Analyze CA Report & Matrix 2B | 12h | 211 |
215 | 788 | Finalize CA Report & Matrix 2B (Meta Review) | 6h | 214 |
247 | 790 | Prepare Base line Report | 52.4d | |
248 | 791 | Identify, Collect &
Document Existing Branch Information | 0.3d | 7.3d |
249 | 792 | Understand Phase 0 CA Selection | 2h | 194 |
250 | 793 | Understand Phase 0 CA Level Of Detail | 3.5h | 249 |
251 | 794 | Review Phase 0 CA Report Outline | 2h | 250 |
253 | 795 | Identify Target Information (See Meta EAS Process Model Pgs.
13-14) | 5h | |
254 | 796 | Collect Target Information | 25h | 253 |
256 | 797 | Consolidate Branch Information Collected | 40.5h | 255 |
268 | 798 | Update Branch Base line Report | 2h | 256 |
257 | 799 | Analyze Branch Information | 2.05d | |
258 | 800 | Review Team Must Prepare For Dialog | 6h | 256 |
259 | 801 | Review Branch Base line Report | 4.5h | 258 |
260 | 802 | Finalize Branch Base line Report | 3h | 259 |
261 | 803 | Deliver Branch Base line Report | 2h | 260 |
263 | 804 | Cleanse Branch Base line Report | 2h | 262 |
264 | 805 | Publish Branch Base line Report | 3h | 263 |
265 | 806 | Consolidate Branch Base line Into EDD Base line | 7.55d | 205 |
266 | 807 | Receive Branch Reports | 2.5h | 264 |
269 | 808 | Consolidate Into EDD Base line | 6h | 268 |
270 | 809 | Finalize EDD Base line Report (Meta Review) | 2h | 269 |
271 | 810 | Deliver EDD Base line Report | 2h | 270 |
272 | 811 | Checkpoint with Josetta | 1h | 271 |
273 | 812 | Cleanse EDD Base line Report | 1h | 272 |
274 | 813 | Publish EDD Base line Report | 2h | 273 |
275 | 814 | Perform Gap Analysis | 10.5d | |
277 | 815 | Prepare for ITDQC, ITET Meeting | 4.5h | |
281 | 816 | ITDQC - Review EDD Base line Report (Current State) | 1h | 280 |
282 | 817 | ITDQC - Review EDD CA Report (Desired State) | 1h | 280 |
284 | 818 | Establish Goals Of This Effort | 5h | 282 |
285 | 819 | Synchronize Participants Understanding Of Goals | 5h | 284 |
286 | 820 | Outline Gap Analysis Report | 5h | 285 |
287 | 821 | Analyze Gaps For Potential Opportunities | 12h | 286 |
288 | 822 | Research Information | 23h | 287 |
293 | 823 | Make Major Decisions & Establish Clear Direction(DIT Mgt.) | 1.5h | 292 |
294 | 824 | Update Gap Analysis Report | 4h | 288 |
296 | 825 | Checkpoint with Josetta | 2h | 294 |
297 | 826 | Review Gap Analysis Report | 12.5h | 296 |
298 | 827 | Finalize Gap Analysis Report (Meta Review) | 10.5h | 297 |
299 | 828 | Final Buy List | 4.5h | 298 |
300 | 829 | Present Phase 2 Deliverable For Commitment | 2.2d | 275 |
301 | 830 | Obtain Commitment/Give Presentation | 2.2d | |
302 | 831 | Coordinate Meeting Room & Date | 0.5h | |
303 | 832 | Invite Participants (ITET, ITDQC) | 0.5h | |
306 | 833 | Prepare Presentation | 6h | 305 |
307 | 834 | Checkpoint with Josetta | 2h | 306 |
308 | 835 | Deliver Phase 2 Deliverable Hard Copy To Attendees | 1h | 307 |
310 | 836 | Execute Presentation | 2h | 309 |
311 | 837 | Checkpoint with Josetta | 2h | 310 |
312 | 838 | Cleanse Phase 2 Deliverable | 2h | 311 |
313 | 839 | Publish Phase 2 Deliverable | 3h | 312 |
304 | 841 | Define Response Required | 1h | 303 |
305 | 842 | Define Time lines For Response | 1h | 304 |
314 | 843 | Consolidate LOB Responses | 1h | 305 |
315 | 844 | Complete Phase 2 | 0d | 193 |
325 | 845 | Phase 3 | 20.7d | 315 |
326 | 846 | Begin Phase 3 | 0d | |
328 | 847 | Initiate Enabling Group For Coordinate & Communicate | 0.5d | |
329 | 848 | Define Mission Of The Team | 2h | |
330 | 849 | Define Goals Of The Team | 2h | 329 |
331 | 850 | Define Deliverable Of The Team | 2.5h | 330 |
332 | 851 | Assign The Team | 2h | 331 |
333 | 852 | Assign Roles & Responsibilities | 3h | 332 |
334 | 855 | Initiate Enabling Group For Research & Educate | 0.5d | |
335 | 856 | Define Mission Of The Team | 2h | 326 |
336 | 857 | Define Goals Of The Team | 2h | 335 |
337 | 858 | Define Deliverable Of The Team | 2.5h | 336 |
338 | 859 | Assign The Team | 2h | 337 |
339 | 860 | Assign Roles & Responsibilities | 3h | 338 |
346 | 863 | Develop On-going Architecture Improvement Strategy | 8.6d | 327 |
347 | 864 | Develop A Common Understanding Of Architecture Improvement
Strategy | 0.5d | |
348 | 865 | Understand Vision | 5h | 327 |
349 | 866 | Divide Into 3 Sub-Teams | 1h | 348 |
350 | 867 | Define The Architecture Improvement Process | 6.95d | |
351 | 868 | Discuss Alternatives With Consulting Partners | 4.5h | 348 |
352 | 869 | Research Best Practices In Other Companies | 24.5h | 351 |
353 | 870 | Develop Recommendation Draft | 11.5h | 352 |
354 | 871 | Checkpoint with Josetta | 2h | 353 |
355 | 872 | Review & Modify Recommendation | 6h | 354 |
357 | 873 | Finalize Recommendation (Meta Review) | 6h | 356 |
358 | 874 | Obtain Approval Of Recommendation | 2h | 357 |
368 | 876 | Define Architecture Leadership Responsibility (Person Or Team) | 7.35d | |
369 | 877 | Discuss Alternatives With Consulting Partners | 5h | 348 |
370 | 878 | Research Best Practices In Other Companies | 23.5h | 369 |
371 | 879 | Develop Recommendation Draft | 12.5h | 370 |
372 | 880 | Checkpoint with Josetta | 2h | 371 |
373 | 881 | Review & Modify Recommendation | 7.5h | 372 |
374 | 882 | Finalize Recommendation (Meta Review) | 6h | 373 |
375 | 883 | Obtain Approval Of Recommendation | 2h | 374 |
376 | 885 | Identify Architecture Maintenance Tools (Current & Desired
State) | 8.6d | |
377 | 887 | Identify CA Maintenance Tools To Review | 24h | |
378 | 888 | Evaluate CA Maintenance Tools | 38h | 377 |
379 | 889 | Select CA Maintenance Tools | 10h | 378 |
380 | 890 | Checkpoint with Josetta | 2h | 379 |
381 | 891 | Install CA Maintenance Tools | 11h | 380 |
382 | 892 | Populate CA Maintenance Tools | 24h | 381 |
383 | 893 | Prepare Migration Strategy Report | 9.35d | 327 |
384 | 894 | Develop Common Understanding Of Migration Strategy Report | 0.7d | |
385 | 895 | Define Purpose Of Migration Plan | 5h | |
386 | 896 | Outline Migration Strategy Report | 3.5h | 385 |
387 | 897 | Develop Migration Strategy Report | 8.65d | 384 |
388 | 899 | Review The Component Architectures | 12.5h | |
389 | 900 | Identify Key Opportunities For Improvements | 22.5h | 388 |
390 | 901 | Provide Recommendation For Strategic Implementation | 47.5h | 389 |
391 | 902 | Draft Migration Strategy Report | 12h | 390 |
392 | 903 | Checkpoint with Josetta | 3h | 391 |
393 | 904 | Modify Migration Strategy Report | 6h | 392 |
394 | 905 | Finalize Migration Strategy Report (Meta Review) | 12h | 393 |
395 | 906 | Present Phase 3 Deliverable For Commitment | 3.4d | 383 |
396 | 907 | Give Presentation | 3.15d | |
397 | 908 | Coordinate Meeting Room & Date | 1h | |
398 | 909 | Invite Participants (ITSMT,ITEI,ITDQC) | 1h | 397 |
399 | 910 | Prepare Presentation | 17h | 398 |
400 | 911 | Checkpoint with Josetta | 2h | 399 |
401 | 912 | Deliver Phase 3 Deliverable Hard Copy To Attendees | 1h | 400 |
404 | 913 | Execute Presentation(Div. Chiefs) | 4h | 403 |
405 | 914 | Cleanse Phase 3 Deliverable | 5h | 404 |
406 | 915 | Publish Phase 3 Deliverable | 2h | 405 |
407 | 916 | Obtain Commitment to Technology Alignment | 0.25d | 406 |
408 | 917 | Define Response Required | 1.5h | |
409 | 918 | Define Time lines For Response | 1.5h | 408 |
410 | 919 | Consolidate LOB Presentation Concerns and Responses | 3h | 402 |
411 | 920 | Complete Phase 3 | 0d | 395 |
421 | 921 | Complete First Iteration of BDAP | 0d | 420 |
119 | 923 | Deliver Phase 1 Deliverable Hard Copy To Attendees | 4h | 118 |
123 | 925 | Cleanse Phase 1 Deliverable | 4.5h | 122 |
214 | 926 | Update CA Report & Matrix 2B (BP x CA) | 12h | 213 |
58 | 934 | Interview for BD | 1h | 57 |
70 | 936 | Review Business Drivers (Executives Only) | 3h | 69 |
87 | 938 | Conduct Interviews if necessary (Executives Only) | 1h | 86 |
94 | 939 | Review AR (Report and Matrix) | 2.5h | 93 |
92 | 940 | (Attach LOB AR Report) & Matrix 1 | 1h | 91 |
93 | 941 | Deliver LOB AR | 1h | 92 |
96 | 942 | Checkpoint with Josetta | 1.5h | 95 |
103 | 944 | Get BU I/T Involvement & Agreement W/ T.T. Report | 1h | 102 |
117 | 946 | Execute Presentation Delivery | 1h | 116 |
120 | 947 | Execute Presentation | 1h | 119 |
122 | 951 | Respond to Phase 1 deliverable | 2h | |
168 | 953 | Checkpoint with Josetta | 1h | 167 |
164 | 954 | Define Principles | 47.5h | 163 |
179 | 958 | Define Best Practice | 47.5h | 178 |
208 | 968 | Infrastructure - Create Component Architectures (Composition) | 29h | 203 |
207 | 969 | Data - Create Component Architectures (Composition) | 18.5h | 206 |
206 | 970 | Applications - Create Component Architectures (Composition) | 63.5h | 203 |
213 | 971 | Checkpoint with Josetta | 2h | 212 |
217 | 972 | Preliminary Buy-in (Josetta ITET) | 1h | 216 |
216 | 973 | Prepare Preliminary Buy-in (Josetta ITET) | 3h | 215 |
255 | 974 | Collect Target Information | 5h | 254 |
262 | 975 | Review Branch Base line Report | 2.5h | 261 |
278 | 976 | Checkpoint with Josetta | 1h | 277 |
279 | 977 | ITET - Review EDD Base line Report (Current State) | 2h | 277 |
280 | 978 | ITET - Review EDD CA Report (Desired State) | 2h | 279 |
291 | 980 | Make Major Decisions & Establish Clear Direction(ITB) | 2.5h | 288 |
290 | 981 | Make Major Decisions & Establish Clear Direction (internal) | 24h | 288 |
309 | 982 | Execute Presentation | 2.5h | 308 |
356 | 984 | Review Presentation | 2h | 354 |
402 | 986 | Execute Presentation (ITET) | 4h | 401 |
403 | 987 | Execute Presentation(ITDQC) | 4h | 402 |
417 | 988 | ID and inventory critical work papers | 4.5h | 411 |
412 | 989 | Project Wrap up | 1.45d | 411 |
418 | 990 | Key factors/Project debrief | 2h | 417 |
419 | 991 | Architecture next steps (6 month plan) | 8.5h | 418 |
420 | 992 | Project close | 10h | 419 |
276 | 993 | Validate Base line Components | 0.8d | |
283 | 994 | Develop draft Gap Analysis | 6.65d | |
289 | 995 | Negotiate Decisions and Establish Direction | 2.85d | |
295 | 996 | Finalize Gap Analysis | 2.7d | |
218 | 997 | Develop Buy List process | 3.1d | |
219 | 998 | Determine process to be used (Consensus, research, baseline) | 20h | 137 |
220 | 999 | Develop process for driving buy lists | 20h | 219 |
17 | 1005 | Execute Communication Plan | 19.35d | 4 |
38 | 1008 | Check Point with Josetta | 1.5h | 37 |
76 | 1009 | Check Point with Josetta | 1.5h | 75 |
106 | 1011 | Checkpoint with Josetta | 1h | 105 |
114 | 1012 | Checkpoint with Josetta | 1h | 113 |
182 | 1013 | Prepare for Checkpoint with Josetta | 2h | 181 |
190 | 1014 | Prepare for Checkpoint with Josetta | 5h | 189 |
292 | 1015 | Make Major Decisions & Establish Clear Direction(DIT tech.) | 1h | 291 |
126 | 1016 | Complete Phase 1 | 0d | 124 |
57 | 1017 | Train LOB Interviewees | 1h | 56 |
171 | 1021 | Map Principles to Architectural Requirements | 4.2d | 170 |
209 | 1022 | Security - Create Component Architectures (Composition) | 21.5h | |
221 | 1049 | Develop Buy List Report | 52.4d | 220 |
222 | 1050 | Data Domain | 4.6d | |
223 | 1051 | Data Transaction Data | 21.5h | 188 |
224 | 1052 | Data Data Warehouse | 22h | 223 |
225 | 1053 | Application Domain | 10.95d | |
226 | 1054 | Application Collaborate/Groupware | 18h | 188 |
227 | 1055 | Application Intranet | 21.5h | 226 |
228 | 1056 | Application Intranet/E-Commerce | 22.5h | 227 |
229 | 1057 | Application Components | 17h | 228 |
230 | 1058 | Applications Applications | 18.5h | 229 |
231 | 1059 | Applications Middleware | 18h | 230 |
232 | 1060 | Infrastructure Domain | 8d | |
233 | 1061 | Infrastructure Platform | 20h | 188 |
234 | 1062 | Infrastructure Network | 19h | 233 |
235 | 1063 | Infrastructure - Systems Management | 21.5h | 234 |
236 | 1064 | Governance Domain | 1.55d | |
237 | 1065 | Governance | 18h | 188 |
238 | 1066 | Security Domain | 1.55d | |
239 | 1067 | Security | 18h | 188 |
240 | 1068 | Update Report | 12h | 220 |
241 | 1069 | Analyze Report | 10.5h | 240 |
242 | 1070 | Checkpoint with Josetta | 2h | 241 |
243 | 1071 | Update Report | 12h | 242 |
244 | 1072 | Finalize Report (Meta
Review) | 6.5h | 243 |
245 | 1073 | Preliminary Buy-in (Josetta ITET) | 3h | 244 |
246 | 1074 | Preliminary Buy-in (Josetta ITET) | 1h | 245 |
19 | 1081 | Execute Communication Plan | 90h | 11 |
22 | 1082 | Brief ITSMT Wrap up | 1h | 21 |
21 | 1083 | Brief ITSMT Status | 2h | 20 |
20 | 1084 | Brief ITSMT on project | 2h | 11 |
4 | 1085 | Project Start up | 2.05d | 3 |
138 | 1086 | Project Start-up | 2.15d | 137 |
151 | 1088 | Execute Communication Plan | 52.4d | 137 |
18 | 1093 | Communication Plan | 19.35d | |
152 | 1094 | Communication Plan | 52.4d | |
153 | 1095 | Execute Communication Plan | 200h | 145 |
154 | 1096 | Brief ITSMT on project | 2h | 145 |
155 | 1097 | Brief ITSMT Status | 1.5h | 154 |
157 | 1098 | Brief ITSMT Wrap up | 2h | 156 |
327 | 1100 | Project start-up | 0.5d | 326 |
340 | 1102 | Execute Communication Plan | 20.2d | 326 |
341 | 1103 | Communication Plan | 20.2d | |
342 | 1104 | Execute Communication Plan | 95h | 334 |
343 | 1105 | Brief ITSMT on project | 1.5h | 334 |
344 | 1106 | Brief ITSMT Status | 1.5h | 343 |
345 | 1107 | Brief ITSMT Wrap up | 1h | 344 |
413 | 1108 | Review Phase | 0.35d | |
414 | 1109 | Develop +/- chart | 2h | |
415 | 1110 | Discuss what can be done to accelerate the Project | 2.5h | 414 |
127 | 1117 | Phase Wrap-up | 1.05d | 126 |
128 | 1118 | Review Phase | 0.45d | |
129 | 1119 | Develop +/- chart | 2h | |
130 | 1120 | Discuss what can be done to accelerate the Project | 3h | 129 |
131 | 1121 | Modify next phase | 0.6d | |
132 | 1122 | Review Project Plan | 2h | 130 |
133 | 1123 | Delete unnecessary tasks | 1.5h | 132 |
134 | 1124 | Add New tasks | 2h | 133 |
135 | 1125 | Advise Project Sponsor | 1h | 134 |
316 | 1126 | Phase Wrap-up | 0.8d | 315 |
317 | 1127 | Review Phase | 0.45d | |
318 | 1128 | Develop +/- chart | 2h | |
319 | 1129 | Discuss what can be done to accelerate the Project | 3h | 318 |
320 | 1130 | Modify next phase | 0.35d | |
321 | 1131 | Review Project Plan | 2h | 319 |
322 | 1132 | Delete unnecessary tasks | 1h | 321 |
323 | 1133 | Add New tasks | 2.5h | 322 |
324 | 1134 | Advise Project Sponsor | 1h | 323 |
416 | 1138 | Review Project | 1.45d | |
156 | 1140 | Brief ITSMT Status | 1h | 155 |
267 | 1178 | BDAP review of product | 4h | 266 |
252 | 1179 | Independent Team Analysis of Baseline | 7.5d | |
359 | 1181 | Develop Governance guidelines | 7.75d | |
361 | 1190 | Discuss Alternatives With Consulting Partners | 5h | |
362 | 1191 | Research Best Practices In Other Companies | 24h | 361 |
363 | 1192 | Develop Recommendation Draft | 12.5h | 362 |
364 | 1193 | Checkpoint with Josetta | 2h | 363 |
365 | 1194 | Review & Modify Recommendation | 7.5h | 364 |
366 | 1195 | Finalize Recommendation (Meta Review) | 6h | 365 |
367 | 1196 | Obtain Approval Of Recommendation | 2h | 366 |
360 | 1198 | Define compliance controls and procedures | 5h | |