Phase Wrap-up

ID

Task Name

Duration

65

Phase Wrap-up

1.11 days

66

Review Phase

0.44 days

67

Develop +/- chart

2 hrs

68

Discuss what can be done to accelerate the Project

2 hrs

69

Modify next phase

0.67 days

70

Review Project Plan

2 hrs

71

Delete unnecessary tasks

1 hr

72

Add New tasks

2 hrs

73

Advise Project Sponsor

1 hr

74

End of Phase

0 days

.

Initial Task List

.

The task set is designed to wrap-up any phase of a development cycle, to learn from mistakes made and to further refine subsequent task sets.

The +/- Chart referred to (ID#67)is also know as a Plus/Delta chart and indicates what is good (Plus) and bad (delta or -) about this phase of the project. Any Delta should be resolved before proceeding with the project.