Start Phase 2 Technical Focus

ID

Task Name

Duration

188

Phase 2 - Technical Focus

.

189

Phase start-up

0 days

190

Review and refine architecture model, determine domains

1 day

191

Develop a graphical representation of the model.

1 day

192

Review Domains and determine what components

4 hrs

193

Review components and determine what sub-components

4 hrs

194

Prioritize components

2 hrs

195

Develop a sample table of contents at the sub-component, component and domain level.

3 hrs

196

Develop Document Structure, templates

1 day

197

Develop Website

5 days

198

Post prior phases on website

1 hr

199

Announce website to all participants of communication plan

1 hr

200

Component Development (for each component)

35 days

.

Initial Task List

.

This task set lays out and refines the product sets that the project will generate, the look and feel of the project. It is suggested that an effort to develop and maintain all records of the project be done on the website. During development, it may be necessary to keep work in draft (straw dogs) in a more confidential area, this can be a set of files shared among the project team.