Project Start Date:
Project Finish Date:
Typical Approval Tasks (Three level approval)
ID |
Task Name |
Duration |
Predecessors |
45 |
IT MGMT TEAM Review |
1.75 days |
41 |
46 |
Schedule IT MGMT TEAM meeting |
2 hrs |
|
47 |
Present Complete Architecture Definition to IT MGMT TEAM |
4 hrs |
46 |
48 |
Incorporate Changes to Architecture Definition |
1 day |
47 |
49 |
IT Knowledgeable Senior Mgmt Review |
6.25 days |
45 |
50 |
Schedule IT Knowledgeable Senior Mgmt meeting |
2 hrs |
|
51 |
Provide document to be discussed (5 day lead) |
5 days |
|
52 |
Present Complete Architecture to IT Knowledgeable Senior Mgmt |
2 hrs |
51 |
53 |
Incorporate Changes to Architecture Definition |
1 day |
52 |
54 |
Enterprise Senior Mgmt Meeting |
6.25 days |
49 |
55 |
Schedule Enterprise Senior Mgmt meeting |
2 hrs |
|
56 |
Provide document to be discussed (5 day lead) |
5 days |
|
57 |
Present Complete Architecture to Enterprise Senior Mgmt |
2 hrs |
56 |
58 |
Incorporate Changes to Architecture Definition |
1 day |
57 |
. |
. |
||
. |
. |
This task set is for a three level approval. In the example case, the leaders of the Information Technology Branch (IT Executive Team -IT MGMT TEAM), the IT cognizant executive staff (IT Department Quality Council - IT Knowlegeable Senior Mgmt), and the Executive staff, some of which are members of the IT Knowlegeable Senior Mgmt (Department Quality Council - Enterprise Senior Mgmt)