Phase 0 Project Planning

ID

Task Name

Duration

1

Phase 0 - Project Planning

288 hrs

2

Setup Week

33 hrs

3

Project kick-off

2 hrs

4

Develop team skills matrix

1 hr

5

Discuss architecture definitions

2 hrs

6

Define project scope

2 hrs

7

Develop project deliverables

1 hr

8

Discuss/define architecture critical success factors

3 hrs

9

Identify team roles

1 hr

10

Identify information sources

2 hrs

11

Identify Sub-Team approach

1 hr

12

Form Sub-Teams

1 hr

13

Organizational planning/administration

3 hrs

14

Identify benefits of architecture

2 hrs

15

Identify costs/risks of architecture

2 hrs

16

Develop architecture timeline

2 hrs

17

Identify architecture resource requirements

2 hrs

18

Identify project roles

2 hrs

19

Finalize project status reporting techniques

2 hrs

20

Refine next sub-phase plan

2 hrs

21

Project Communications Plan

88 hrs

.

Initial Task List

.

This task set sets the tone for the project, including working interfaces, level of staff and management involvement.

It also indicates what the commitment of the staff and management of the project is and will allow adjustments early on in the project.