Develop the Communication Plan

ID

Task Name

Duration

1

Phase 0 - Project Planning

288 hrs

21

Project Communications Plan

88 hrs

22

Develop Communications Plan matrix

1 hr

23

Develop time/resource template

1 hr

24

Review Communications Plan matrix

2 hrs

25

Identify stakeholders

2 hrs

26

Validate stakeholders

2 hrs

27

Develop draft Communications Plan

6 hrs

28

Develop project organization chart

4 hrs

29

Finalize Communications Plan

2 hrs

30

Develop mail lists (both Email and hand delivery)

2 hrs

31

CIO Review of Draft Communications Plan

6 hrs

32

Incorporate CIO 's changes

2 hrs

33

Project Continuation Signed-off

2 hrs

34

Develop Project Plan

128 hrs

.

Initial Task List

.

The Communication Plan is critical to the project success. It indicates what effort by staff other than the project team is going to be required. It gives time frames for management to schedule staff and themselves, it is the primary tool to aachieve enterprise commitment and buy-in. You will not get commitment if you can't get scheduled for a manager's or their staff time!