Project Start Date:
Project Finish Date:
Phase 1 Business Side of the Architecture
Start-up
ID |
Task Name |
Duration |
77 |
2.44 days |
|
78 |
Redefine team into sub-teams based on skills matrix (Phase 0) |
1.11 days |
79 |
Define Mission Of The Team |
2 hrs |
80 |
Define Goals Of The Team |
2 hrs |
81 |
Define Deliverable Of The Team |
4 hrs |
82 |
Assign The Team |
2 hrs |
83 |
Assign Roles & Responsibilities |
2 hrs |
84 |
End Planning |
0 days |
87 |
280 hrs |
|
. |
. |
It is necessary for the forming of the team to enable the cohesive work that is necessary for the development of the architecture.