EWITA

Project Start Date:
Project Finish Date:

Execution of Communications Plan

ID

Task Name

Duration

77

Phase 1 - Project Start up

2.44 days

87

Execute Communication Plan

280 hrs

88

Brief Senior IT Managers on project

1 hr

89

Brief Senior IT Managers Status

1 hr

90

Senior IT Managers Contact LOB Managers

25 hrs

91

Interview Sub-project start

0 days

92

Interview setup

6 days

93

Develop Interview List

8 hrs

94

Notify Interviewees

1 hr

95

Schedule interviews

5 days

96

Develop interview questions

8 hrs

97

Email questions to participants, hard copies follow

0.53 hrs

98

Interview process

3.23 days

.

Initial Task List

.

This task set is necessary for the validation and set up of the interviews for the Communication Plan.

In an organization (Large State Organization) of 13000 people about 60 key managers were interviewed, including all of Enterprise Executive staff, the communication plan was validated by the Senior IT Mgmt Team. One of the questions asked of all participants was "Is there some one else that should participate in this interview.