Project Start Date:
Project Finish Date:

Prepare and Develop Architectural Requirements

ID

Task Name

Duration

77

Phase 1 - Project Start up

2.44 days

87

Execute Communication Plan

280 hrs

98

Interview process

3.23 days

131

Prepare Architecture Requirements Report & Matrix 1 (BD x AR)

12.85 days

132

Using Communications Plan determine LOB executives

2 hrs

133

Coordinate AR Development Session

2 hrs

134

Identify Information Required to Support BD

10 hrs

135

Identify the Processes That Generates AR

11.5 hrs

136

Derive AR From Data & Process Input

20 hrs

137

Conduct Interviews if necessary (Executives Only)

1 hr

138

Update AR Report & BD x AR Matrix

8 hrs

139

Define Response Time lines

2 hrs

140

Prepare Thank You Letter, Attach LOB AR Report & BD x AR Matrix

1 hr

141

Schedule face to face meeting with LOB executives

1 hr

142

Hand Deliver LOB AR Report & BD x AR Matrix

1 hr

143

Review AR Report & BD x AR Matrix, request validation

2 hrs

144

Receive validated AR Report & BD x AR Matrix

6 hrs

145

Checkpoint with CIO

1 hr

146

Finalize LOB AR Report & BD x AR Matrix

4 hrs

147

Prepare Technology Trends (TT) Report

5.81 days

.

Initial Task List

.

The development of Architectural Requirements (ARs) is a technical review of the Business Requirements and the determination of the minimum required to meet the Business Requirements. For instance the requirement for sub second response time has a totally different requirement for monthly reports. Capacities, equipment, personnel and site should be considered when developing the ARs.