Project Start Date:
Project Finish Date:
Presentation for Commitment
ID |
Task Name |
Duration |
77 |
2.44 days |
|
87 |
280 hrs |
|
98 |
3.23 days |
|
131 |
Prepare Architecture Requirements Report & Matrix 1 (BD x AR) |
12.85 days |
147 |
5.81 days |
|
157 |
4.89 days |
|
158 |
Define Time lines For Response |
1 hr |
159 |
Coordinate Meeting Room & Date |
4 hrs |
160 |
Invite Participants (document review management levels) |
2 hrs |
161 |
Prepare Presentation/Deliverable |
15 hrs |
162 |
Checkpoint with CIO |
1 hr |
163 |
Deliver Phase 1 Deliverable email to first level review attendees, follow with hard copies |
1 hr |
164 |
Execute Presentation Preparation |
2 hrs |
165 |
Execute Presentation Delivery |
1 hr |
166 |
Modify Phase 1 Deliverable, if required |
4 hrs |
167 |
Deliver Phase 1 Deliverable email to second review attendees, follow with hard copies |
1 hr |
168 |
Execute Presentation Preparation |
2 hrs |
169 |
Execute Presentation Delivery |
1 hr |
170 |
Modify Phase 1 Deliverable, if required |
4 hrs |
171 |
Deliver Phase 1 Deliverable email to executive level review attendees, follow with hard copies |
1 hr |
172 |
Execute Presentation Preparation |
2 hrs |
173 |
Execute Presentation Delivery |
1 hr |
174 |
Modify Phase 1 Deliverable, if required |
4 hrs |
175 |
Coordinate and Consolidate LOB Responses |
1 hr |
176 |
Publish Phase 1 Deliverable |
2 hrs |
177 |
Complete Phase 1 |
0 |
178 |
1.11 days |
|
. |
. |
For executive buy-in this presentation of the findings is critical for success. The modification of the final report reflecting the input of the reviews represents the "final" concerns of the management of the enterprise